some-alt
ДТЭК
Our company
Sustainable development
Investor relations
Team
Media center
Toggle High Contrast
EN
UA
Homepage Media center Press Releases
  • Homepage
  • Media center
  • Press Releases
  • Filling up the foundations and looking for financing: how DTEK Tyligulska WPP project is progressing
28 June 2023, ukraine_country_name

Filling up the foundations and looking for financing: how DTEK Tyligulska WPP project is progressing

PDF version
Download
download
Subscribe to our news linkedin
Filling up the foundations and looking for financing: how DTEK Tyligulska WPP project is progressing

Following the commissioning of the first stage of Tyligulska WPP, DTEK Renewables team continued to work on tasks to complete the construction of the wind farm to the design capacity.

Among the important works taking place at the wind farm site is the process of preparing to pour 21 foundations for turbines.

The process requires the use of a special mortar, the so-called "liquid stone," which must be poured continuously and hardens very quickly.

"We will have a new experience as a customer and work supervisor, and not through the general contractor, as it was before," said Kostiantyn Bakharev, technical supervision manager.

That is why the contractors will be tasked with ensuring that 11.5 tons of mortar are added to each foundation and that the equipment is washed. After all, the mixture gains 50% strength in just half an hour.

"If the technology is not followed, the foundations have to be broken and poured anew," explains Kostiantyn Bakharev.

The site is also used to re-preserve unused components for the wind turbines and to hydro-insulate the finished foundations.

At the same time, DTEK Renewables is discussing with various equipment suppliers the possible delivery dates for components for the second stage of the wind farm and is looking for financing for the project.

All news
All news
New energy-efficient windows installed in the surgical unit of Berezanka hospital
27 June 2025
New energy-efficient windows installed in the surgical unit of Berezanka hospital
Potlavska Wind Farm paid UAH 1.5 million to Globyne community for land lease
25 June 2025
Potlavska Wind Farm paid UAH 1.5 million to Globyne community for land lease
DTEK Renewables Completes Professional Energy Storage System Management Course with Fluence
20 June 2025
DTEK Renewables Completes Professional Energy Storage System Management Course ...
DTEK Renewables Pays UAH 339.5 Million in Taxes in Q1 2025
11 June 2025
DTEK Renewables Pays UAH 339.5 Million in Taxes in Q1 2025
ДТЭК
Our company
Sustainable development
Investor relations
Team
Media center
DTEK Renewables
in social media
footer socials ceo
© 2006-2024. DTEK
All rights reserved
Made by Frontmen, 2020
EN
UA
Our company
Sustainable development
Investor relations
Team
Media center
Согласен Не согласен